To install a drip edge on a newly constructed roof or on a re roofing job attach the drip edge along the roof s eaves first.
Proper installation of roof drip edge.
Align the leading bottom edge of the first piece on the gable rake with the front edge of the drip edge installed on the eave.
Slide the corner tight to the fascia.
Be sure to tuck the drip edge under the starter strip and felt paper.
Make sure the outer edge extends over the gutter.
On the gable rake install drip edge starting at the bottom and working up.
The drip edge should be nailed centered in the top surface every 8 to 10 inches.
How to install drip edge flashing to a new roof.
It can be done.
Use a flat pry bar and hammer to pry the nails out of the drip edge gently.
The above figure shows the correct application of the drip edge.
Once free slide the drip edge out and discard.
Slip the wide flat flange of the material all the way under the first course of roof shingles as illustrated.
The roof leg should extend a minimum of 2 back onto the roof sheathing.
While the vertical leg should be placed 1 4 1 2 away from the fascia.
Make sure the corner is tight and that the bottom edge is tight to the fascia before nailing off the drip edge.
If it doesn t pull the drip edge out slightly from under the shingles.
You may need to nail through the starter strip into the drip edge.
Place a nail at one end then the other.
At the rake the drip edge is installed over the underlay.
Secure the drip edge with roofing cement.
How to install a drip edge.
Gently lift up the shingles on the edge of the roof and locate the nails holding the existing drip edge onto.
Make sure to support the long end of the cut if you let it fall after cutting it will bend down and kink the drip edge.
No cutting is needed for this piece.